放線(xian)工作根據(ju)(ju)土建實際的中心(xin)線(xian)及標高點(dian)進行;飾面的設計以建筑物的軸線(xian)為依據(ju)(ju)鋁塑板(ban)骨架由橫豎(shu)件(jian)(jian)組成,先彈好豎(shu)向(xiang)桿件(jian)(jian)的位(wei)置線(xian),然后再將(jiang)豎(shu)向(xiang)桿件(jian)(jian)的錨(mao)固點(dian)確定。
安裝固(gu)定(ding)連接件(jian)(jian)(jian)在(zai)放線的基礎(chu)上(shang)(shang),用電(dian)焊(han)(han)固(gu)定(ding)連接件(jian)(jian)(jian),焊(han)(han)縫(feng)處防銹漆二度。連接件(jian)(jian)(jian)與(yu)主(zhu)體(ti)結構上(shang)(shang)的預埋(mai)件(jian)(jian)(jian)焊(han)(han)接固(gu)定(ding),當主(zhu)體(ti)結構上(shang)(shang)沒有埋(mai)設(she)預埋(mai)鐵件(jian)(jian)(jian)時,可在(zai)主(zhu)體(ti)結構上(shang)(shang)打孔安設(she)膨脹螺栓與(yu)連接鐵件(jian)(jian)(jian)固(gu)定(ding)。
安(an)裝(zhuang)骨架用(yong)焊(han)(han)接(jie)方法安(an)裝(zhuang)骨架,安(an)裝(zhuang)隨時檢(jian)(jian)查標高,中心線位置(zhi)(zhi)(zhi),并同(tong)時將截(jie)面連接(jie)焊(han)(han)縫做(zuo)防(fang)銹漆處理,固定連接(jie)件做(zuo)隱蔽檢(jian)(jian)查記錄包括連接(jie)件焊(han)(han)縫長度(du)、厚度(du)、位置(zhi)(zhi)(zhi)埋置(zhi)(zhi)(zhi)標高、數量、嵌入深度(du)。
安裝(zhuang)鋁塑(su)(su)板(ban)在型材內架(jia)上,先攻銑螺絲孔位(wei),用鉚釘將鋁塑(su)(su)板(ban)飾面逐塊固定在型鋼(gang)骨架(jia)上;板(ban)與板(ban)之間的間隙為10~15㎜再注入硅酮耐候(hou)密封膠(jiao);鋁板(ban)安裝(zhuang)前嚴禁拆包(bao)裝(zhuang)紙,直(zhi)至竣工前方撕(si)開(kai)包(bao)裝(zhuang)保護膜;根(gen)據鋁塑(su)(su)板(ban)箭(jian)頭指示方向施(shi)工。